CB Resources logo

Step 1. The DYCD-funded provider (prime contractor) establishes a relationship with a resource provider (subcontractor) and decides to bring the resource’s services to the program.

Step 2The prime contractor speaks with their DYCD. Program Manager to ensure they are able work with a subcontractor and that it is permissible within the terms and conditions or contract.

Step 3If the prime contractor is able to bring on a subcontractor, the following actions and documents must be submitted to the assigned DYCD Program Manager for approval:

Step 4.  The DYCD Program Manager will review the Subcontractor Agreement and Subcontractor Approval Form and submit them for approval by the Deputy Director.

Step 5.  If approved, the DYCD Program Manager submits the Subcontractor Agreement and Subcontractor Approval Form to the Agency Chief Contracting Officer (ACCO) unit for vetting.

Step 6.  The ACCO unit will vet the subcontractor by checking:

  1. a) Payee Information Portal (PIP)

** We recommend subcontractors enroll in PIP as soon as possible to avoid delays in processing a subcontract. **   Information on PIP is available at

https://a127-pip.nyc.gov/webapp/PRDPCW/SelfService

 

  1. b) PASSport (Procurement and Sourcing Solutions Portal)
  1. c) Google search
  2. d) Uniform Commercial Code (IRS liens)
  3. e) NYS Charities Bureau, if applicable

Step 7The DYCD ACCO unit will approve /disapprove the subcontractor – this information is then sent back to the DYCD Program Manager, who will inform the prime contractor.

Step 8The DYCD Program Manager contacts the prime contractor to determine next steps:

**Please note: DYCD ACCO unit will only contact the prime contractor for information/ documentation needed from the subcontractor.  DYCD ACCO will not contact the subcontractor. It is up to the prime contractor to communicate with the subcontractor regarding missing documents or other needed items.  DYCD ACCO COMMUNICATES ONLY WITH THE PRIME CONTRACTOR.

Step 9Upon an executed/approved subcontract, the resource provider can begin rendering services for the prime contractor (DYCD-funded provider/program) enhancing high quality programming.

Step 10The subcontractor is paid directly by the prime contractor (DYCD-funded provider/program) for services rendered.  NYC DYCD DOES NOT PAY THE SUBCONTRACTOR.*Note: A subcontractor who is operating without prior approval form DYCD is operating at risk to the Prime provider.  DYCD will not reimburse any work performed by an unapproved subcontractor.

Procurement questions can be directed to the DYCD Agency Chief Contracting Officer (ACCO) Unit at acco@dycd.nyc.gov or (646) 343-6399.

 

Summary of Required Subcontractor Documents

Requirement Organizations that have Previously Worked with NYC Organizations New to Working with NYC
1 Subcontract Agreement (3 original notarized copies) ü Required – Prime Contractor submits to DYCD ü Required – Prime Contractor submits to DYCD
2 Subcontractor Approval Form Prime Contractor completes          and submits to DYCD with Subcontract Agreement Prime Contractor completes          and submits to DYCD with Subcontract Agreement
3 PIP Enrollment ü Required – Subcontractor should enroll ASAP to avoid procurement delays ü Required – Subcontractor should enroll ASAP to avoid procurement delays
4 VENDEX Contract History   If organization is registered in VENDEX but does not have VENDEX contract history, 3 references from comparable projects required 3 references from comparable projects required from Subcontractor
5 Certificate of No Change (CONC) Form If organization is in VENDEX and has a City funding aggregate of over $100K N/A